Green Lantern Continues to Grow Ahead of Maiden MRE
Summary
Pantoro Limited (ASX:PNR) (Pantoro) is pleased to advise that the Green Lantern mineralisation, an extensive zone near surface adjacent the existing Scotia Open Pit at the Norseman Gold Project continues to prove up, with the most recent round of infill drilling focussed on finalising a Maiden Resource estimation.
Key Highlights
Results provide confidence that mine life from the Scotia Mining Centre will be extended beyond the current Phase One feasibility plan.
Drilling undertaken to support Mineral Resource Estimation and Ore Reserve Calculation for initial open pit mining. The orebody has been delineated over a strike length of approximately 800 metres and remains open to the south and down dip.
Deeper drilling in the latest round has returned wide, high grade intersections at depth, demonstrating additional underground potential following completion of open pit.
Commenting on the results Pantoro Managing Director Paul Cmrlec said:
“Green Lantern is a great exploration success story for the Norseman Gold Project, and highlights the opportunities available due to the lack of exploration activity in the area for the past 25 years. The Scotia Mining Centre is already a one of our major ore sources in the planed operations restart at Norseman, and we are confident that a sustained drilling effort will continue to extend mine life and productivity in the area.”
Green Lantern
Green Lantern lies approximately 270 metres to the South East of the Scotia Open Pit, and is open at depth and along strike to the South. The southern most drill line completed to date is typical of the Green Lantern deposit generally with no indication that the system is weakening along strike.
The current drilling which is designed to achieve spacing suitable for Ore Reserve calculation, has continued to increase confidence infilling multiple lodes. and further refined understanding of the orientation of the lode system and controls on mineralisation. Pantoro is nearing completion of sufficient drilling required in the area to complete a maiden Mineral Resource Estimate. Results indicate a wide lode system as well as a narrower high grade system along the entire strike at Green Lantern.
About the Norseman Gold Project (Pantoro 50%)
Pantoro Limited announced the major acquisition of 50% of the Norseman Gold Project in May 2019 and completion occurred on 9 July 2019. Pantoro is the manager of the unincorporated joint venture, and is responsible for defining and implementing work programs, and the day to day management of the operation.
The Norseman Gold Project is located in the Eastern Goldfields of Western Australia, at the southern end of the highly productive Norseman-Wiluna greenstone belt. The project lies approximately 725 km east of Perth, 200 km south of Kalgoorlie, and 200 km north of Esperance.
The project comprises 146 near-contiguous mining tenements, most of which are pre-1994 Mining Leases. The tenure extends approximately 70 lineal kilometres of the highly prospective Norseman–Wiluna greenstone belt covering approximately 800 square kilometres.
Historically, the Norseman Gold Project areas have produced over 5.5 million ounces of gold since operations began in 1935, and is one of, if not the highest grade fields within the Yilgarn Craton.
The current Mineral Resource is 4.3 million ounces of gold (100% basis). Many of the Mineral Resources defined to date remain open along strike and at depth, and many of the Mineral Resources have only been tested to shallow depths. In addition, there are numerous anomalies and mineralisation occurrences which are yet to be tested adequately to be placed into Mineral Resources, with a number of highly prospective targets already identified by drilling.
Pantoro has focused initial project planning on six initial mining areas containing multiple deposits which are amenable to both open pit and underground mining. A Phase One DFS was completed in October 2020 detailing an initial seven year mine plan with a centralised processing facility and combination of open pit and underground mining producing approximately 108,000 ounces per annum. A new one million tonne per annum processing plant is to be constructed by GR Engineering following an extensive tendering process.