I note in the 5B that ARU's SPP was expanded and scaled back significantly.
Originally looking to raise $12M, they expanded it to $20M and even then "scaled back to 26% of the application amount".
Normally you'd expect a cap raise to depress the price but both the placement and the SPP had significant scale-back. (Placement was about 30% of bid.) Note, that there are still $25M for tranche II of the placement pending. Should settle in the next week. That gives a total raise of $141M - about 10% of the capex required.
The scale-back explains the high on-market demand. I think that taking a little extra in the SPP was prudent - these projects tend to go over budget. Hopefully this is enough equity to allow finance funding that will get Nolans to cash flow positive.
Pre-production capex estimated at $A 1,394M ($1.5B with contingency). So an extra $8M is not material.
"Advancement and negotiation of the finance facilities are targeted to allow for FID in March 2023 with contractual close on project financing to follow in mid-2023"
Base case NPV of $2.4B, upside of $4.2B (with higher NdPr price).
Got to love that Nolans is "one of the only advanced NdPr ore to oxide projects of scale in the western world."