at 4/1/22: Rincon 2,000tpa Li2CO3 Operational Update ( was price sensative )
Summary
Argosy Minerals advised further progress at the Rincon Lithium Project, located in Salta Province, Argentina, with 53% of the total works completed for the development of the modular 2,000tpa lithium carbonate production operation. The Company remains on schedule to achieve first production of 99.5% battery quality lithium carbonate product from mid-2022. The 2,000tpa production operation major works comprise three main phases of works, comprising design, construction and commissioning. The design phase works (including engineering layout) are complete (100%), the construction phase is currently at 55% completion, whilst plant commissioning works (comprising raw materials acquisition and tender works) are 13% complete.