Pinned straw:
This was further buried in the quarterly for June 2025

40K tonnes a month mined.
DVP is currently hitting 650Ktpa of ore processed so the mining rate needs to increase significantly from here now ramp up is happening (maybe to 60K a month at least).
So a long way to go before we consider 1mtpa.
Furthermore this is more a Zinc than copper mine. Same as Sulphide Springs. So there could be some volatility in cashflow.